Particulars |
Value |
• Date of sanction | 01/01/1967 |
• Proposed Mine Capacity | San Francisco |
• Proposed Capital | 1 |
• Mineable Reserve | 34.52 MT |
• Life | 33 Yr |
• Average Stripping Ratio | 19.68 Cum/T |
• Land | 735.00 Ha |
• Scheduled date of completion | 8th Yr |
• Anticipated date of completion | 2028 |
• 1st year of production as per PR | 3rd Yr |
• Yr. of achieving targeted production | 4th Yr |
• Actual date of production | 01/01/1967 |
Particulars |
Value |
• Date of sanction | 10-07-2008 |
• Sanctioned Mine Capacity | 0.25 MTY |
• Sanctioned Capital | Rs. 56.39 Cr. |
• Mineable Reserve | 5.19 MT |
• Life | 26 Yrs. |
• Average Stripping Ratio (Cum./ Te) | 13.36 Cum/T |
• Land | 235 Ha (Forest) |
• Scheduled date of completion | 6th Yr |
• Anticipated date of completion | October, 2023 |
• 1st year of production as per PR | 4th Yr |
• Yr. of achieving targeted production | 6th Yr |
• Actual date of production | Not yet started. |
PROJECT REPORT |
||
Sl No |
Activity |
Status |
1. |
Date of approval of PR |
Approved by ESC of CIL Board in its 68th meeting held on 10/07/2008 with Hiring /Outsourcing option. |
2. |
Revised Cost Estimate |
|
LAND USE |
||
Sl No |
Activity |
Status |
1. |
Land Area |
235.00 Ha (Reserve Forest). |
FOREST CLEARANCE |
||
Sl No |
Activity |
Status |
1. |
Date of Application Submitted |
01.01.2008 for 235.0 Ha (Reserve Forest) |
2. |
Stage –I FC |
Received – 28.03.2013 F. No.8-5/2012-FC |
3. |
Stage-I FC Compliance |
Preparation of wildlife Management Plans
Under compliance of Stage I conditions, State Forest Dept. has placed a demand notice to pay Rs.35.15 Cr. towards NPV/CA/Overhead charge on 03-11-2014. CIL advised to go for Updated Cost Estimate of Lekhapani PR, as the total cost of CA+NPV is not fully provisioned in PR. NEC has written to CMPDIL on 15-4-15 for updation of cost estimate. Updated Cost Estimate for Lekhapani OCP submitted by CMPDIL. But, NEC has written to CMPDI for certain modification. Updated Cost Estimated received from CMPDIL on 27th January, 2016.Updated Cost Estimate put up for approval of CIL Board on 05.02.2016. However, PMD Division of CIL has advised some correction in the report which has been forwarded to CMPDIL for correction. CMPDI has informed that RCE of Lekhapani has been completed and dispatched to NEC, which is yet to be received. However, a soft copy of the report has been sent to CIL, PMD. After coal price reduction, the Recast PR has been updated by CMPDIL. The CA estimate for Safety Zone and estimate for Safety Zone afforestation has been forwarded by DFO, Digboi to Conservator of Forest, Jorhat on 11/08/2016 . CA estimate forwarded to Addl PCCF (T) on 20/08/2016 by Conservator of Forest, Jorhat. |
Clearance under Scheduled Tribes and other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 – Obtained from DC, Tinsukia Assam, on 5th Aug 2 011 vide TPL.197/2002-03/193
Particulars |
Value |
• Date of sanction | 13-05-2011 |
• Sanctioned Mine Capacity | 1.00 MTY |
• Sanctioned Capital | 260.15 (Outsourcing) 683.27 (Departmental) |
• Mineable Reserve | 19.03 MT |
• Life | 25 Yrs. |
• Average Stripping Ratio | 15.77 Cum/T |
• Land | 783.69 Ha |
• Scheduled date of completion | 6th Yr. |
• Anticipated date of completion | March 2026 (under FC) |
• 1st year of production as per PR | 4th Yr |
• Yr. of achieving targeted production | 6th Yr |
• Actual date of production | Not yet started. |
FOREST CLEARANCE |
||
Sl No |
Activity |
Status |
1. |
Date of Application |
On 16.05.2013 for diversion of 691.80 Ha |
2. |
Stage-I FC |
• Pending for recommendation of Divisional Forest Officer Part-II: The enumeration has been completed on 04.02.2015 |