TIRAP OCP PHASE-II
1. Capacity : 0.60 Million Tonnes per Annum for normative capacity and 0.80 for peak production.
2. Sanctioned amount : Rs.49.71 Crores
3. Date of approved by : Approved by CIL Board in 68th meeting held on
CIL Board and 10.07.2008 Matter confirmed vide No.CIL:PM:21:272
letter Ref. dated 15th July, 2008
4. Form-I submission : Form-1 submitted to MoEF, New Delhi vide
No.43011/109/2008-CPAM dt.3st October, 2008 by
Section Officer, Ministry of Coal, Govt. of India,
New Delhi.
5. TOR meeting : Meeting of EAC for finalization of TOR held on
and Ref. 26.11.2008. TOR received from MoEF, New Delhi
vide No.J-11015/461/2008-IA.II(M) dated 11th
December, 2008 for only 0.40 MTPA. Requested to
Director, MoEF, New Delhi for review the case for
TOR for 0.60 MTPA for normative capacity and 0.80
MTPA in peak production period. Corrigendum
received from MoEF vide No.J-11015//461/2008- IA.II(M) dt.10th January, 2008.
6. Land Status : Total land required = 516 Hects. Out of which 289
Hects. falls within forest land and balance 227 Hects.
in private land owner’s land. Application for diversion
of forest land for non-forest purposed submitted to
State Forest Department, Assam vide No.NEC/L&R/
2008/TRP(OC)/231 dt.30.09.2008